What Are Construction Submittals? A Guide for Commercial Project Owners

October 12, 2026

Construction submittals are the shop drawings, product data, samples, mockups, and other documents a contractor sends to the architect, engineer, or owner for review before materials are ordered, fabricated, or installed. They confirm that what the contractor plans to build matches the drawings and specifications. For owners, submittals are the last practical point to catch the wrong finish, a problem product, or a long lead time before it becomes an expensive change in the field. They are not a way to change the project's scope; that still requires a change order.


Hartford Building Company is a woman-owned, licensed, insured, and bonded general contractor in Glastonbury, Connecticut, bringing four decades of industry experience to commercial interior fit-outs, office, school, hospital, hotel, and restaurant renovations, and architectural millwork installation. We prepare, track, and coordinate submittals on every commercial project we build, and this guide explains the process from the owner's side of the table.


In This Guide


What Submittals Are and Why They Exist

Construction drawings and specifications describe what the finished project should be. They usually do not show every product model, fabrication detail, or installation method. Submittals fill that gap.


Showing How the Work Will Be Built

When a contractor or subcontractor submits a shop drawing or product data sheet, they are showing exactly how they plan to meet the design. The architect or engineer checks it against the design intent and specifications. If something does not match, it gets corrected on paper instead of on site.


Where Submittal Requirements Come From

Submittal requirements are written into the project specifications, typically in a general requirements section on submittal procedures, and in each technical section that lists what must be submitted. Standard contracts, such as AIA's A201 General Conditions, also define the main submittal types and each party's responsibilities.


What Submittals Are Not

Under common contract forms, submittals are not contract documents. An approved submittal does not change the contract, the scope, or the price. If the owner wants something different from what was designed, that change goes through a change order, not a submittal.


The Main Types of Submittals

Most commercial projects involve several kinds of submittals. The table below shows the common ones and what they tell the review team.

Submittal Type What It Is What Reviewers Check
Shop drawings Detailed drawings prepared for the project by the contractor, a sub, or a fabricator Dimensions, materials, connections, and fit with surrounding work
Product data Manufacturer cut sheets marked to show the exact model and options Whether the product meets the specified performance and features
Samples Physical pieces of finishes such as flooring, tile, paint, laminate, or veneer Color, texture, and finish match the design
Mockups Full-size sample installations built on or off site Appearance, workmanship, and how assemblies come together
Certifications and test reports Documents showing compliance with codes, standards, or fire ratings Required ratings, testing, and approvals
Closeout submittals Warranties, operation and maintenance manuals, and record drawings Completeness before final payment and turnover

Shop Drawings

Shop drawings are the most detailed and most important submittals on many projects. For architectural millwork, casework, storefronts, and specialty items, they show exactly what will be fabricated. Our guide to millwork shop drawings walks through them in detail.


Samples and Mockups

Samples and mockups are where owners have the most direct input. A finish that looks right on a screen can look different in real light, next to other materials. Reviewing physical samples prevents surprises when the space is finished. We recommend looking at samples in the actual space whenever possible, under the lighting that will be installed, and next to the other finishes they will sit beside. A laminate that pairs well with a flooring sample on a conference table can clash once both are installed across a full room.


How the Submittal Process Works

The exact steps vary by project and contract, but most commercial submittals follow the same path.



Step by Step

  1. The subcontractor or supplier prepares the submittal based on the specifications.
  2. The general contractor reviews it for completeness, coordination with other trades, and field conditions, then stamps and forwards it.
  3. The architect or engineer reviews it against the design intent and specifications.
  4. The reviewer returns it with an action stamp and any comments.
  5. The contractor either proceeds with ordering or fabrication, or revises and resubmits.


The Submittal Log

A good contractor tracks every required submittal in a log or register, with the specification section, responsible sub, date submitted, date returned, review status, and lead time. The log is one of the best tools owners have for spotting delays early. Ask to see it at project meetings, and ask which open items could affect your move-in date.


How RFIs Connect

If a contractor finds a conflict or gap in the drawings while preparing a submittal, the question should go through a request for information before the submittal is finalized. Resolving the question first prevents a submittal from being rejected for reasons that were never the contractor's to decide.


What Review Stamps Mean

Reviewers use a short set of actions on every submittal. Wording varies by firm, but the meaning is usually the same:



  • Approved or No Exceptions Taken: The contractor can proceed as submitted.
  • Approved as Noted or Make Corrections Noted: The contractor can proceed, but must follow the reviewer's comments.
  • Revise and Resubmit: Changes are needed, and the contractor must submit again before proceeding.
  • Rejected: The submittal does not meet the requirements and must be replaced.
  • For Information Only or Not Reviewed: The document was received but did not require formal review.


Approval does not relieve the contractor of responsibility for meeting the contract documents. It confirms the submittal appears to conform to the design intent. That shared responsibility is part of why careful review on both sides matters.


What Owners Should Review

Owners do not need to review every submittal. Most technical submittals, such as structural connections, fire alarm devices, or mechanical equipment, are best reviewed by the design team. There are areas, though, where owner input is valuable:


  • Finish samples in visible areas, such as flooring, wall finishes, laminates, veneers, and paint.
  • Millwork and casework shop drawings for reception desks, nurse stations, hotel front desks, and other signature pieces.
  • Mockups of repeating elements, like a hotel guest room or a classroom layout.
  • Equipment that affects operations, such as kitchen equipment, security hardware, or technology that your staff will use every day.
  • Items with long lead times that could affect your opening or move-in date.
  • Maintenance-sensitive products your facilities team will have to service.



Bringing your facilities or operations staff into these reviews often catches practical issues designers miss, like a finish that is hard to clean or a lock that does not work with your access system.


Submittals and the Schedule

Submittals are often on the critical path, especially for renovations with tight deadlines.


Lead Times Start After Approval

For many products, the manufacturer's lead time does not start until the submittal is approved and the order is released. Items like custom millwork, storefront systems, door hardware, specialty lighting, and HVAC equipment can take weeks or months. A two-week delay in review can push an opening date by two weeks or more.


Review Time Is Part of the Plan

Specifications usually allow a set period for review. Building that time into the schedule, and prioritizing long-lead submittals early, keeps the project moving. On phased projects, such as school renovations that must finish during summer break or hotel renovations floor by floor, early submittals are often what make the schedule possible.


How Owners Can Help

Make decisions on samples and selections quickly, designate one person to speak for the owner, and avoid reopening decisions after approval. Every revision cycle adds time.


Substitutions and Changes

Sometimes a contractor proposes a product different from what was specified. That is a substitution, and it follows its own rules.


When Substitutions Come Up

Common reasons include a discontinued product, a long lead time that threatens the schedule, a cost savings opportunity, or a better-performing alternative. Substitutions are often part of value engineering, where the team looks for options that meet the same function at a better total cost.


How They Should Be Handled

Specifications usually require substitution requests to be clearly identified, with a side-by-side comparison to the specified product. The design team should review performance, appearance, warranty, and code implications. If the substitution changes cost or scope, it should be documented formally. A substitution slipped into a routine submittal without being flagged is a red flag.


Closeout Submittals

Submittals do not end when construction does. Closeout submittals are the records owners keep for the life of the building.


What You Should Receive

Expect warranties, operation and maintenance manuals, record or as-built drawings, product information for finishes, and attic stock such as extra tile or ceiling panels when specified. For systems like HVAC, fire protection, and controls, expect test reports and training for your staff.


Why They Matter

Closeout documents help your facilities team maintain the space, order matching materials for repairs, and handle warranty claims. They also make the next renovation easier. Store them digitally and confirm they are complete before final payment. For a broader look at how projects are delivered, see our overview of turnkey construction services.


Common Submittal Problems and How to Avoid Them

Submittal issues rarely make headlines, but they cause many of the delays and disputes on commercial projects.


Where Things Go Wrong

The most common problems are incomplete submittals that get rejected, submittals passed along without the contractor's own review, late submittals for long-lead items, owners reopening decisions that were already approved, and substitutions that are not clearly identified. On renovations, another frequent issue is shop drawings based on the original drawings instead of field measurements. Existing walls are rarely perfectly square or where the old plans say they are, and millwork or storefront built to the wrong dimensions does not fit.


How to Prevent Them

Most of these problems can be prevented with a complete submittal log at the start of the project, clear responsibilities for each item, early attention to long-lead products, field verification before fabrication, and regular log review at project meetings. Involving the contractor early through preconstruction services makes it easier to plan submittals before the schedule gets tight.


Work With a Contractor Who Manages Submittals Well

A well-run submittal process is invisible to most owners. They just see a project that stays on schedule and finishes the way it was designed. Hartford Building Company manages submittals on every commercial project we build, from interior fit-outs and office remodeling to millwork installation. You can see examples in our projects.


Call Hartford Building Company at (860) 922-0179 or contact us to talk about your next commercial project in Connecticut.


Frequently Asked Questions

  • What is a submittal in construction?

    A submittal is a document, drawing, or physical sample a contractor sends to the architect, engineer, or owner for review before ordering, fabricating, or installing materials. Common submittals include shop drawings, product data, samples, and mockups.

  • Who approves construction submittals?

    The architect or engineer usually reviews and takes action on submittals, after the general contractor has reviewed them first. The owner may also review items like finish samples and millwork drawings, depending on the contract and the owner's preferences.

  • What is the difference between a submittal and an RFI?

    A submittal shows how the contractor plans to meet the design. An RFI, or request for information, asks the design team to clarify something unclear or conflicting in the drawings or specifications. RFIs are often resolved before a related submittal is finalized.

  • Does an approved submittal change the contract?

    No. Under most standard contracts, submittals are not contract documents and do not change the scope, price, or schedule. Changes to the contract require a formal change order.

  • How long does submittal review take?

    Review periods are usually set in the project specifications and often range from about one to two weeks per submittal, sometimes longer for complex items. Resubmittals add another review cycle, so early and complete submittals help protect the schedule.

Recent Blog post

Construction plans with hard hat, tape measure, pen, blueprint tube, and a hand holding dollar bills
October 1, 2026
What is value engineering in construction? A Connecticut general contractor explains how VE protects budget without sacrificing quality, with key examples.
Team members in safety vests and office clothes review plans around a table with papers and a coffee cup.
September 15, 2026
What are preconstruction services? A CT contractor explains how early planning, estimating, and constructability review cut project cost, risk, and delays.
Two people talking in a bright, empty room with large windows.
September 15, 2026
Leasehold vs. tenant improvements explained: what each one is, who pays, who owns the work, and what happens at lease end, from a CT commercial contractor.
Worker in a yellow hard hat measuring a wooden board in a workshop, with another worker in the background
August 19, 2026
What are millwork shop drawings? Learn what they include, who reviews and approves them, and how they keep commercial millwork on schedule, from a CT firm.
Modern dining room with wood-slat walls, long table, and chairs by a large window
August 19, 2026
What is architectural millwork? Learn the common types, materials, AWI grades, and the key install steps for commercial CT projects from a trusted GC firm.
Construction workers in hard hats and vests at a building site with scaffolding and a crane
July 12, 2026
What is turnkey construction? Learn how the turnkey model works, what it includes, its pros and cons, and who it's the right fit for on a building project.