Construction Change Orders Explained: Causes, Costs, and How to Reduce Them
A construction change order is a written agreement that changes the scope, price, or schedule of a construction contract after it has been signed. Change orders happen when the owner adds or changes work, when the drawings contain errors or missing information, when crews uncover hidden conditions in an existing building, or when code officials or material availability require something different. Some change orders are unavoidable, especially in renovations. The goal is not zero change orders but fewer surprises: clear documents, a realistic contingency, early decisions, and a fair, transparent process for pricing and approving changes.
Hartford Building Company is a woman-owned, licensed, insured, and bonded general contractor in Glastonbury, Connecticut, bringing four decades of industry experience to commercial interior fit-outs and renovations for offices, schools, hospitals, hotels, restaurants, and manufacturing facilities. Managing changes fairly and transparently is one of the most important parts of keeping a project on budget. This guide explains why change orders happen, how they are priced and approved, and what owners can do to keep them under control.
In This Guide
- What a Change Order Is: The basics.
- The Most Common Causes of Change Orders: Why they happen.
- Who Typically Pays for Changes: A quick reference.
- How the Change Order Process Works: Step by step.
- How Change Orders Are Priced: Lump sum, unit price, and time and materials.
- How Contract Type Affects Change Orders: Lump sum, GMP, and more.
- Change Orders and the Schedule: Time impacts.
- How to Review a Change Order: What owners should check.
- How to Reduce Change Orders: Practical strategies.
- Budgeting a Contingency: Planning for the unknown.
- Frequently Asked Questions: Quick answers.
What a Change Order Is
A Formal Contract Amendment
A change order modifies the original contract. It describes the change in work, the adjustment to the contract price, and any adjustment to the schedule. Once signed, it becomes part of the contract.
Who Signs It
On many commercial projects using AIA contract documents, a change order is signed by the owner, the contractor, and the architect. All parties agree on the work, the price, and the time.
Related Tools
When a change needs to start before price and time are agreed, a construction change directive can authorize the work while the terms are settled. Minor changes that do not affect cost or time can be handled by the architect through supplemental instructions. Questions about the documents are handled through RFIs, which may or may not lead to a change order. Our guide on
what an RFI is in construction
explains that step.
The Most Common Causes of Change Orders
Owner-Requested Changes
The owner decides to add a room, upgrade finishes, relocate walls, or add equipment after the contract is signed. These are the most controllable changes, and they tend to be most expensive when made after materials are ordered or work is installed.
Design Errors and Omissions
Drawings may contain conflicts, missing details, or elements that do not work as drawn. Correcting them can add cost.
Unforeseen or Concealed Conditions
In renovations, opening walls, floors, and ceilings can reveal rot, structural problems, undocumented utilities, hazardous materials, or past alterations that were never recorded.
Code and Inspection Requirements
Building officials or fire marshals may require changes during review or inspection, especially in older buildings being brought closer to current code.
Material Availability and Lead Times
Specified products may be discontinued or delayed, requiring substitutions that change cost or schedule.
Schedule Changes
Owner-requested acceleration, delays in owner decisions, or changes to phasing in occupied buildings can add labor or general conditions costs.
Tenant or User Changes
On fit-out projects, tenant requirements sometimes evolve during construction, such as new furniture layouts or added data and power.
Who Typically Pays for Changes
Responsibility depends on the contract, but these patterns are common.
| Cause of Change | Who Usually Pays | How to Reduce the Risk |
|---|---|---|
| Owner-requested scope changes | Owner | Finalize decisions before bidding; limit changes during construction |
| Design errors and omissions | Owner, with possible recovery from the designer depending on the agreement | Constructability reviews and complete documents |
| Concealed conditions in existing buildings | Owner, under typical concealed-conditions clauses | Investigate existing conditions before final design |
| Code and inspector requirements | Usually owner, if not shown in the documents | Early code review and coordination with officials |
| Contractor errors or poor coordination | Contractor | Choose an experienced, well-organized contractor |
| Material substitutions requested by the contractor | Contractor, unless approved as a cost change | Approve substitutions through submittals |
Contract language controls these outcomes, so review it with your legal and design team.
How the Change Order Process Works
- A change is identified, through an owner request, an RFI answer, a field discovery, or an inspector's comment.
- The contractor reviews the impact with subcontractors and suppliers.
- A change proposal is prepared, describing the work, the cost, and any schedule impact.
- The architect and owner review the proposal, ask questions, and request backup where needed.
- The parties negotiate if pricing or time needs adjustment.
- The change order is signed by the required parties.
- The work proceeds, and the change is tracked in the change order log.
- The schedule of values and project schedule are updated, and the change is reflected in payment applications.
Why Written Approval Matters
Verbal approvals in the field lead to disputes later. Even urgent changes should be documented in writing, using a change directive if final pricing is not ready. A short email confirming the direction is better than nothing, but a formal document protects everyone.
How Change Orders Are Priced
Lump Sum
The contractor provides a fixed price for the change, with supporting detail. This is the most common approach for well-defined changes.
Unit Pricing
Some contracts set unit prices in advance, such as a price per linear foot or per square foot. Unit prices simplify pricing when quantities are uncertain.
Time and Materials
When the scope cannot be defined in advance, work may be billed based on actual labor, materials, and equipment, plus agreed markups. Owners should require daily documentation of crews, hours, and materials so the final bill can be verified.
Markups and Backup
Contracts usually define allowable overhead and profit percentages on changes. Owners should expect a breakdown showing labor, materials, subcontractor costs, and markups rather than a single number.
Credits
Not every change adds cost. Deleting scope or simplifying a detail should produce a credit.
How Contract Type Affects Change Orders
Lump Sum Contracts
With a fixed contract price, any change in scope requires a change order. Clear documents matter most here, because anything not shown in the drawings becomes a potential change.
Guaranteed Maximum Price
Under a guaranteed maximum price, the contractor's costs are tracked against a ceiling. Changes in scope adjust the maximum, while some coordination items may be covered by a contractor's contingency inside the price.
Cost-Plus Contracts
When the owner pays actual costs plus a fee, changes are tracked through costs as they occur. Transparency and regular reporting are essential so the owner can see how decisions affect the total.
Design-Build
Because design and construction are under one contract, many design coordination issues are resolved internally rather than becoming owner change orders. Owner-requested changes still require formal approval.
Change Orders and the Schedule
Time Impacts
Changes can add time when they affect work on the critical path, require new materials with long lead times, or add inspections. A change in a finished area at the end of the job may have little schedule effect, while the same change to framing or ductwork early on can ripple through several trades.
Requesting Time
Contractors typically must request schedule extensions with the change proposal. Owners should look for a clear explanation of why the change affects the completion date.
Hidden Costs of Delay
Even when a change seems small, extended schedules can increase general conditions costs, such as supervision, temporary facilities, and equipment.
Occupied Buildings
In schools, hospitals, and hotels, schedule changes can affect operations, such as a classroom returning late or guest rooms staying out of service longer.
How to Review a Change Order
Before signing, owners should ask:
- Is this truly a change, or is the work already included in the contract documents?
- What caused the change, and is the cause documented?
- Is the scope clearly described, with drawings or sketches if needed?
- Is the pricing broken down into labor, materials, subcontractors, and markups?
- Are the markups consistent with the contract?
- Is there a credit for any work being removed?
- Does the change affect the schedule, and is the time request explained?
- Are there alternatives that would cost less or take less time?
Working With Your Architect
The architect can help evaluate whether a change is justified and whether pricing is reasonable. On design-build projects, the design and construction team work together to present options. Our article on
design-build vs. traditional construction explains how delivery methods affect change management.
How to Reduce Change Orders
Invest in Preconstruction
Involving the contractor during design allows constructability reviews, realistic budgets, and early identification of problems. Our guide to preconstruction services explains how this works.
Make Decisions Before Construction
Finalize layouts, finishes, equipment, and furniture before bidding whenever possible. Late decisions are one of the most common causes of owner changes.
Investigate Existing Conditions
In renovations, above-ceiling surveys, selective demolition, and hazardous materials testing before final design reduce surprises.
Use Value Engineering Early
Value engineering is most effective during design, not after construction starts. Our article on value engineering in construction explains the timing.
Manage Submittals and RFIs Promptly
Quick, clear answers keep small questions from turning into costly delays. Our guide on what construction submittals are covers that process.
Choose an Experienced Contractor
A contractor with experience in your building type knows where surprises tend to hide and can plan for them.
Budgeting a Contingency
Owner's Contingency
Owners commonly set aside a contingency, often a percentage of construction cost, to cover changes and unknowns. Renovations of older buildings generally warrant a larger contingency than new construction or straightforward fit-outs.
Contractor's Contingency
Some contracts include a contractor's contingency for items within the contractor's scope, such as coordination issues. How it is used and whether unused funds return to the owner should be spelled out in the contract.
Allowances
Allowances set budgets for items not yet selected, such as specific light fixtures or finishes. If the final selection costs more or less than the allowance, the difference is adjusted through a change order.
Tracking Contingency Use
Regular reports showing how contingency is being used help owners make informed decisions about optional upgrades. If contingency is being used faster than expected early in the project, it is a signal to slow down optional changes.
Change Orders in Real Projects
In tenant fit-outs, a common change is adding data or power locations after the furniture layout is finalized. In school renovations, hidden conditions behind classroom walls or above ceilings are frequent. In facility upgrades, such as our renovation of an employee facilities room at the Duro Bag manufacturing facility in Meriden, coordinating new finishes and fixtures with existing plumbing and building systems is where questions often arise. Experienced teams anticipate these issues, price them fairly, and keep the owner informed so decisions are made quickly.
Talk to a Connecticut Commercial General Contractor
If you are planning a renovation or fit-out and want a contractor who manages changes clearly and transparently, our team would be glad to help. Learn more about our general contracting services, see our projects, or read more about our company.
Call Hartford Building Company at (860) 922-0179 or
contact us. We are located at 22 Kreiger Lane in Glastonbury and serve commercial clients throughout Connecticut.
Frequently Asked Questions
What is a change order in construction?
A change order is a written amendment to a construction contract that changes the scope of work, the contract price, the schedule, or a combination of these after the contract is signed.
What causes most change orders?
Common causes include owner-requested changes, design errors or omissions, hidden conditions in existing buildings, code requirements, and material availability issues.
Who pays for change orders?
It depends on the cause and the contract. Owners typically pay for scope changes and concealed conditions, while contractors are generally responsible for their own errors.
How can I reduce change orders on my project?
Involve your contractor in preconstruction, finalize decisions before bidding, investigate existing conditions, answer questions promptly, and budget a realistic contingency.
Can a contractor refuse to do a change order?
Contracts often allow owners to direct changes within the general scope of the work, with price and time adjusted fairly. The specific rights depend on the contract language.